Giant Mine Remediation Project - EA0809-001
Document List
Letters from Northern Project Management Office to Yellowknives Dene and North Slave Metis Alliance regarding the Giant Mine Remediation Report of EA and Reasons for Decision.
This is a letter from the Minister of Aboriginal Affairs and Northern Development Canada to the Review Board Chairperson regarding the decision and final measures.
This is the Minister of AANDC's response to Alternatives North letter of April 28, 2014 regarding inspections at Giant Mine.
This is a letter from Alternaitves North to the Minister of AANDC regarding inspections at Giant Mine.
This joint letter from the YKDFN, the City of Yellowknives and Alternatives North asks responsible ministers to accept the Giant Report of EA measures with proposed modifications, and conclude the EA.
This is the Review Board's response to the Responsible Ministers' suggested modifications to certain measures from the Report of EA. It includes the Board's recommended revisions.
These are Alternatives North's comments on the ministers' suggested modifications to measures from the Giant Report of EA.
These are the NSMA's comments on the ministers' suggested modifications to measures from the Giant Report of EA.
These are the YKDFN's comments on the ministers' suggested modifications to measures from the Giant Report of EA.
These are the City of Yellowknife's comments on the ministers' suggested modifications to measures from the Giant Report of EA.
These are the developer's comments on the ministers' suggested modifications to measures from the Giant Report of EA.
This letter provides information on the Jan. 20th 2014 working meeting, which is part of the consult-to-modify process for the Giant EA. It includes an agenda.
This letter describes the consult-to-modify process to consider modifications to certain measures from the Report of EA.
This is a letter from NPMO to the Tlicho Government requesting comments on proposed modifications to the Review Board's measures from the Giant Report of EA
This is a letter from NPMO to the NSMA requesting comments on proposed modifications to the Review Board's measures from the Giant Report of EA
This is a letter from NPMO to the YKDFN requesting comments on proposed modifications to the Review Board's measures from the Giant Report of EA
This is a letter from the Minister of Aboriginal Affairs and Northern Development Canada to the Mackenzie Valley Review Board initiating consultation to proposed modification of 9 measures.
This is the YKDFN's response to the developer's comments about the Report of EA.
This is the City of Yellowknife's response to the developer's comments about the Report of EA.
This is the City of Yellowknife's response to the developer's comments about the Report of EA.
This is Alternatives North's response to the developer's comments about the Report of EA. Includes Nov. 14 working group meeting summary, draft Environmental Agreement, media coverage and chronology.
This is the reply from AANDC to MP Dennis Bevington's letter of Oct. 7 2013 regarding the Giant Report of EA.
This document contains three excerpts from the hansard of the Legislative assembly regarding questions about the Giant EA. This was submitted to the public registry by MLA Bob Bromley.
This Note to File is a disclaimer regarding recent materials posted to the Public Registry.
This is MLA Bob Bromley's Member's Statement of Nov. 4, 2013 regarding the Giant Team response to the environmental assessment. It was submitted by Bob Bromley's office.
This is a letter from CanNor on behalf of Responsible Ministers. It invites the Tlicho Government to submit its comments on the developer's analysis of the environmental assessment by Nov. 29, 2013.
This is a letter from CanNor on behalf of Responsible Ministers. It invites the NSMA to submit its comments on the developer's analysis of the environmental assessment by Nov. 29, 2013.
This is a letter from CanNor on behalf of Responsible Ministers. It invites the YKDFN to submit its comments on the developer's analysis of the environmental assessment by Nov. 29, 2013.
This letter from AANDC on behalf of Responsible Ministers encourages parties to submit their responses to the environmental assessment by Nov. 29 2013.
This is a letter and detailed attachment describing the Giant Team's review and comments on the Report of EA, along with a covering letter from NPMO.
This e-mail from Alternatives North includes an excerpt of the hearing transcript discussion the role of the Giant Team in the review of the Report of EA.
This document, submitted by Alternatives North, is a motion and related transcript of the NWT Legislative Assembly regarding the Giant Mine Report of EA on October 21, 2013.
This is a letter from Member of Parliament Dennis Bevington to federal ministers regarding the Giant Mine Report of EA.
This letter from AANDC Minister Valcourt acknowledges the August 7th 2013 letter from MLAs W. Bisaro, B. Bromley and R. Hawkins regarding the Giant Report of Environmental Assessment.
This is a letter from the City of Yellowknife to Responsible Ministers regarding the Giant Report of Environmental Assessment.
This is a letter about the Giant Mine Report of Environmental Assessment from the YKDFN to federal and territorial ministers.
This letter from the North Slave Metis Alliance provides comments on the Giant Report of EA. It was sent to the NPMO.
This letter from the Yellowknives Dene provides comments on the Giant Report of EA. It was sent to the NPMO.
Letter from 3 Members of the NWT Legislative Assembly to responsible Ministers regarding the Giant Remediation Project Report of EA.
These City of Yellowknife Council Meeting minutes of July 8 2013 includes a motion that was passed regarding the Giant Report of Environmental Assessment.
This is a Weledeh / Dogrib translation of the decision, executive summary, conclusions, measures and suggestions of the Giant Report of Environmental Assessment, translated at the request of YKDFN.
Letters from Northern Projects Management Office to Aboriginal organizations
This is the Review Board's Report of Environmental Assessment for the Giant Mine Remediation Project.
This is a news release regarding the Giant Report of EA.
This is a media advisory indicating that the Board will release its Report of EA on the proposed Giant Mine Remediation Project on June 20th, 2013 at 9:30 am.
This is one of two reports submitted in response to part three of the Review Board's February 2013 information request.
This is one of two reports submitted in response to part three of the Review Board's February 2013 information request.
This is a table provided by AANDC containing additional information on engineered wetlands for water treatment at Giant Mine.
This is additional information on water treatment alternatives provided by AANDC in response to questions from YKDFN.
This is an e-mail from DFO regarding the developer's 2013 IR responses.
This is a letter from Alternatives North containing their comments on the developers March 2013 IR responses to the Review Board's February 2013 Information Request on the proposed diffuser.
This is a report by AECOM and SENES prepared in response to the Review Board's February 2013 information request regarding water treatment alternatives.
This is the developer's response to the Review Board's March 2013 information request regarding water treatment and release alternatives.
This is one of four attachments to the letter of March 8, 2013 from AANDC to the MVLWB regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of four attachments to the letter of March 8, 2013 from AANDC to the MVLWB regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of four attachments to the letter of March 8, 2013 from AANDC to the MVLWB regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of four attachments to the letter of March 8, 2013 from AANDC to the MVLWB regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This letter of March 8, 2013 from AANDC to the MVLWB describes emergency work on the roaster and underground stabilization at the Giant mine site.
This letter informs parties of the deadline for comments on the developer's March 2013 IR responses.
This is a letter from the Review Board to the MVLWB regarding the EA scope and the emergency work proposed at the Giant mine site.
Letter from AANDC to Review Board re: emergency work at Giant Mine site
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This letter from the Review Board to the developer discusses s.119 emergency work on the roaster and underground stabilization, and the scope of the environemental assessment.
This letter from the Review Board to the developer grants one additoional week for the current Information Request response.
This is a request from the developer for a one-week extension to the Board's response deadline for the current Information Request
This is an information request to the developer regarding the proposed diffuser. It includes a covering letter to parties stating that the Board is re-opening the record for this subject only.
This is one of INAC's / AANDC's remaining responses to the first round of information requests from the Review Board.
This is one of INAC's / AANDC's remaining responses to the first round of information requests from the Review Board.
The following document contains Environment Canada's final comments regarding the Review Board's environmental assessment of the Giant Mine Remediation Project.
This is a Note to File regarding the participation of Board member John Curran in this environmental assessment.
There are the closing comments from Alternatives North