Diamond Exploration - EA1112-001

Document List

Displaying 116 documents.
1.77 MB

This is the Federal Court judgement on the Debogorski judicial review.

436.32 KB

This is a letter from the YKDFN to the MVLWB regarding the Debogorski exploration project,

378.35 KB

This is a Federal Court notice of application for YKDFN vs Attorney General of Canada and Alex Debogorski

739.38 KB

This is a letter the Mackenzie Valley Land and Water Board sent to its distribution list indicating Alex Debogorski's Land Use Permit Application MV2011C0002 is now proceeding to the regulatory phase.

43.45 KB

This is the letter of transmittal for the EA1112-001 Report of Environmental Assessment and Reasons for Decision

1.48 MB

This is the Report of Environmental Assessment and Reasons for Decision for Alex Debogorski's proposed Diamond Exploration Project

263.19 KB

The attached media advisory indicates the Review Board will release its Report of EA and Reasons for Decision for Alex Debogorski's proposed Diamond Exploration Project on January 6th, 2012 at 3 pm (MST).

393.74 KB

This is a note to file advising parties that the public record for EA1112-001 - Debogorski Diamond Exploration project will close at 5pm on Monday October 31st.

6.62 MB

This is NPMO's undertaking from the October 12th Debogorski public hearing in N'dilo.

101.6 KB

This is the response from AANDC regarding undertakings number one and two from the October 12 Debogorski public hearing.

396.39 KB

This is the transcript for the Debogorski public hearing held in N'dilo on October 12, 2011

38.65 KB

This is a letter from the Review Board to parties regarding the undertakings from the October 12th hearing.

122.35 KB

This is the Yellowknives Dene First Nation's undertaking from the Encore Renaissance (formerly CGV) hearing.

204.89 KB

This is the AANDC undertaking from the Encore Renaissance (formerly CGV) public hearing.

181.59 KB

This is the updated transcript from the Encore Renaissance (formerly CGV) Septepber 12th hearing in N'dilo.

72.36 KB

This is a note to file stating that the September 12th, Encore Renaissance hearing transcript has been replaced with an updated version.

129.1 KB

This is the sign in sheet from the October 12th hearing for EA 1112-001.

427.31 KB

This is the presentation from the Treaty 8 Tribal Corporation IMA implementation office.

357.83 KB

This is the Yellowknives Dene First Nation presentation for the Debogorski hearing.

148.21 KB

This is a letter from Deninu Kue First Nation to the Review Board stating that they will not be in attendance at the Debogorski Hearing but support the Yellowknives Dene First Nations postition.

1.46 MB

This is a presentation from the North Slave Metis Alliance for the Debogorski Hearing on October 12, 2011.

155.26 KB

This is the submission from Akaticho Treaty 8 Tribal Coporation - IMA Implementation Office

3.19 MB

This is the final submission from the Government of the Northwest Territories.

18.36 KB

This is the outline for the YKDFN's presentation at the Debogorski hearing.

559.02 KB

This as a letter from the Review Board providing parties with a draft hearing agenda and advising that the deadline for final submissions has been extended to Friday October 7th at noon.

992.51 KB

This is the final submission from Alex Debogorski for EA1112-001.

665.55 KB

This is a letter dated September 12, from YKDFN to the Review Board regarding the CGV and Debogorski Hearings.

423.42 KB

This is a resolution from the Dene National Assembly Resolution regarding mineral exploration in Drybones Bay. It was submitted as exhibit 2 at the Encore Renaissance (CGV) Public Hearing on September 12, 2011.

1.49 MB

This is the presentation from Akaitcho Treaty 8 Tribal Council for the September 12 & 13 Encore Rennaissance (CGV) Public Hearing.

54 KB

This is a letter dated July 22, 2011 from Aboriginal Affairs and Northern Development to North Slave Metis Alliance, acknowledging the information required by Canada to assess North Slave Metis Alliance's Aboriginal rights assertions.

56.21 KB

This is the 2007 UN Declaration of Indigenous Rights submitted by the North Slave Metis Alliance.

248.25 KB

These are the transripts from the Encore Renaissance public hearing on September 13.

311.78 KB

This is an updated work plan for EA 1112-001.

99.95 KB

This is an agenda for the October 3rd pre-hearing conference.

208.78 KB

This is a note to file stating that the Akaitcho IMA Implementation office has been granted party status for EA1112-001.

700.77 KB

This is a letter from the Review Board to parties advising that the Debogorski hearing has been rescheduled for October 12 & 13.

187.96 KB

This is a note to file to provide parties with additional details and an agenda for the pre-hearing conference.

254.86 KB

This is a letter from the GNWT to the Review Board dated August 29th providing an addendum to IR02.

289.8 KB

This is a note to file that provides additional details about the Debogorski hearing, including date, time, location, and the shuttle bus schedule between Dettah and N'dilo.

605.39 KB

This is a letter from the Review Board to YKDFN stating that they will not defer the Debogorski hearing.

61.08 KB

This is a letter from YKDFN dated August 22, 2011 requesting that transcripts from YKDFN testimony at the CGV hearing on September 12 &13 be copied to the Debogorski EA registry.

1.27 MB

This is the report of environmental assessment for North American General Resources EA03-003. On August 22, 2011 YKDFN submitted this document to the public registry for EA 1112-001.

1.16 MB

This is the report of environmental assessment for Consolidated Goldwin Ventures EA03-002. On August 22, 2011 YKDFN submitted this document to the public registry for EA 1112-001.

2.09 MB

This is the report of environmental assessment for Sidon International Resources Corp. EA0506-006. On August 22, 2011 YKDFN submitted this document to the public registry for EA 1112-001.

1.71 MB

This is the report of environmental assessment for Consolidated Goldwin Ventures. On August 22, 2011 YKDFN submitted this document to the public registry for EA 1112-001.

883.25 KB

This is the report of environmental assessment for Snowfield Development - EA 03-006. On August 22, 2011 YKDFN submitted this document to the public registry for EA 1112-001.

1.16 MB

This is the report of environmental assessment for New Shoshoni Ventures - EA03-004. On August 22, 2011 YKDFN submitted this document to the public registry for EA 1112-001.

45.56 KB

This is a letter dated August 15 from YKDFN to the Board requesting the hearing be delayed by 30 days.

634.32 KB

This is a letter from the Review Board to the distribution list advising that financial support will be provided to out-of-town parties to travel to Yellowknife to particiapte in the hearing.

37.48 KB

This is a letter from the developer dated August 15th providing approximate GPS coordinates of the initial two drill-holes.

439.91 KB

This is a letter from the Review Board to the developer to follow up on his commitment to provide GPS coordinates for his initial two drill locations.

252.68 KB

This is a note to file to notify parties that confidential archaeological reports have been placed on the record. It also describes the process to view them.

8.02 MB

This a summary of the community information session held in Dettah on July 20th with attachments including the developer's Powerpoint Presentation and the session Sign-In Sheet.

97.37 KB

This is a letter advising the Board that the developer may not be present on September 14, 2011.

156.12 KB

This is a note to file advising parties that the pre-hearing conference has been changed to Friday September 2nd.

184 KB

This is an email exchange between YKDFN and the Consultation Support Unit, AANDC regarding Crown Consultation.

37.62 KB

This is an email from Deninu Kue First Nation Explaining Why they did not attend the Debogorski Community Information Session.

213.7 KB

This is a note to file notifying parties that the date of the community hearing has been set for September 14 & 15.

161.46 KB

This is a letter dated August 4th from the GNWT including a response to the Board's Information Request #2.

129.42 KB

This is a letter dated August 3, 2011 from the Yellowknives Dene First Nation to the Review Board requesting additional documents be transferred to the public registry.

49.19 KB

This is an email from LKDFN advising the Board that they will not be attending the Debogorksi Community Information Session.

251.37 KB

Note to File - DKFN absence from Community Information Session

240.14 KB

This Note to File describes the July 13, 2011 site visit to Debogorski's proposed project area.

4.48 MB

This is an updated Mineral Claim Sheet Map submitted by Alex Debogorski to the Review Board on July 20th.

185.89 KB

This note to file provides an update on the road conditions to Dettah on July 19th.

782.75 KB

This is a letter from the Yellowknives Dene First Nation dated July 15th, providing comments about the community information session stage.

371.17 KB

This is a note to file about the transfer of evidence to the public registry for EA 1112-001

34.28 KB

This is an email from North Slave Metis Alliance stating they do not have staff or resources to attend the Debogorski Community Information Session.

876.66 KB

This is an Information Request to the Prince of Wales Northern Heritage Centre from the Review Board.

208.13 KB

This Note to File provides details about the shuttle bus that will run between N'dilo and Dettah to provide transportation for parties and community members to attend the Community Information Session for the Debogorski EA.

98.39 KB

This is a letter dated July 6, 2011 from the Yellowknives Dene First Nation regarding the Community Information Sessionm scheduled for July 20, 2011 in Dettah.

2.82 MB

This is the Review Board's Reasons for Decision on the YKDFN's May 27th request for ruling.

838.54 KB

This a cover letter notifying parties of the July 20th Community Information Session for the proposed Debogorski Diamond Exploration Project, which will be held in Dettah. It also inlcudes an agenda and description of the information session.

233.45 KB

This is a note to file that states that a wall-poster sized map depicting the land tenure for the area surrounding Debogorski's mineral claim, as of May 19, 2011, is available to be viewed at the Review Board office.

1.12 MB

This is the Information Request response from Alex Debogorski to the Review Board dated June 19, 2011.

190.94 KB

This is a note to file to notify parties that the North Slave Metis Alliance has been granted party status.

565 KB

This is a letter from the Board to to the Yellowknives Dene First Nation regarding their May 27th Request for Ruling.

95.03 KB

This is a letter dated June 6, 2011from Lutsel K'e Dene First Nation, providing comments on the Yellowknive's Dene First Nation's May 27th Request for Ruling.

140.53 KB

This is a letter from NSMA dated June 3, 2011 providing comments on the YKDFN's May 27th Request for Ruling.

280.81 KB

This is a document from Deninu Kue First Nation received on June 3, 2011 providing comments on the YKDFNs May 27th Request for Ruling.

151.4 KB

This is a letter from the GNWT dated June 3, 2011 providing comments on the YKDFN's May 27, 2011 Request for Ruling.

139.86 KB

This is a letter from INAC dated June 3, 2011 providing comments on the YKDFN's May 27, 2011 Request for Ruling.

840.37 KB

This is a letter from the Review Board to parties requesting comments on the YKDFN's Request for Ruling by Monday June 6th, 2011.

250.75 KB

This is a Request for Ruling from the Yellowknives Dene First Nation dated May 27, 2011.

565.59 KB

Cover letter and Information Request from the Review Board to Alex Debogorski - EA1112-001

1.34 MB

Final Work Plan for EA 1112-001 - Debogorski Diamond Exploration Project - Drybones Bay

602.41 KB

Work Plan cover letter dated May 27th from the Review Board to the distribution list.

222.72 KB

Note to file stating the Review Board has granted official Party Status to YKDFN, LKDFN, DKFN, INAC, and the GNWT for EA 1112-001 - Debogorski Diamond Exploration Project.

27.34 KB

Summary of the May 18, 2011 meeting between Alex Debogorski, government representatives, and the MVLWB. Valley Land and Water Board

118 KB

Letter dated May 20th from LKDFN to the Review Board providing comments on the draft Work Plan for Debogorski Diamond Exploration Project, Drybones Bay and Requesting Party Status.

124.16 KB

Letter dated May 20th from INAC to the Review Board providing comments on the draft work Plan for EA 1112-001 - Debogorski Diamond Exploration Project, Drybones Bay

27.96 KB

Letter of May 20th from Alex Debogorski regarding the draft Work Plan for EA 1112-001

356.08 KB

Letter dated May 20th from YKDFN re: the draft Work Plan for Debogorski EA 1112-001.

140.36 KB

Letter from GNWT providing comments on the draft Work Plan for the Debogorski EA 1112-001.

9.05 MB

Additional Information from Alex Debogorski about location options for initial drilling and archaeological assessments near the proposed project area.

64.75 KB

Fax Distribution List for May 10th Cover Letter, draft Work Plan, request for Party Status Form.

1.28 MB

Draft Work Plan for Debogorski EA dated May 10, 2011.

81.83 KB

Request for Party Status form - attachment to letter of May 10th requesting comments on the draft Work Plan and request for party status.

1.06 MB

May 10th letter from the Review Board requesting comments on the draft Work Plan and requesting party status applications.

61.28 KB

Note to file summarizing the April 20th meeting between the developer and Review Board staff.

732.94 KB

Letter from MVLWB to the Review Board notifying of referral of Debogorski Diamond Exploration Project, Drybone Bay to EA.

268.49 KB

Letter dated March 29, 2011 from INAC to MVLWB providing comments on LUP application.

2.27 MB

MVLWB Staff Report dated March 30, 2011.

516.3 KB

Letter dated March 3, 2011from MVLWB requesting comments on LUP application.

1.94 MB

Land Use Permit Application.

157.44 KB

Letter dated March 3, 2011 from MVLWB to the Developer notifying that the LUP application was deemed complete.

45.28 KB

Letter dated March 28, 2011 from LKDFN to MVLWB providing comments on LUP application.

411.23 KB

Letter dated March 15, 2011 from YKDFN to MVLWB providing comments on LUP application.

106.78 KB

Email of March 11, 2011 from INAC to MVLWB providing comments on LUP application.

117.17 KB

Letter dated March 30 from ENR to MVLWB providing comments on LUP application.

53.21 KB

Letter dated March 30, 2011 from EC to MVLWB providing comments on LUP application.

86.21 KB

Letter dated March 24, 2011 from DOT to MVLWB providing comments on LUP application.

632.4 KB

Email dated March 11, 2011 from DFO to MVLWB providing comments on LUP application.

263.98 KB

Letter dated February 11, 2011 from the MVLWB to the Developer stating that the LUP application was deemed incomplete.

205.63 KB

LUP Application - Additional Project Information from Developer to MVLWB - dated February 22, 2011

1.07 MB

Letter of notification to the developer from the Review Board of EA Start-up - Debogorski Diamond Exploration - Drybones Bay