Mineral Exploration at Howard's Pass (Selwyn Project) - EA0708-001 [2007]
0.1 MBFinal letter to SLWB from INAC
A clarification letter from INAC to SLWB regarding the Selwyn Project. This letter dated September 30, 2009, states the position of all the Respoonsible Ministers regarding the issuance of the permit for the Project.
| Received: | Sep 30, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Federal or responsible minister |
| Public Registry: | 79 |
| Stage: | Other public registry materials |
0.5 MBIssuance of permit for Selwyn Project
Permit for Selwyn Project.
| Received: | Sep 30, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Other |
| Public Registry: | 80 |
| Stage: | Other public registry materials |
0.06 MBCover Letter to Minister Strahl for Selwyn REA
The covering letter attached to the Selwyn Report of Environmental Assessment sent to the Minister of Indian and Northern Affairs July 3, 2009.
| Received: | Jul 6, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 77 |
| Stage: | Report of Environmental Assessment/Impact Review |
2 MBReport of Environmental Assessment for Selwyn Resources Ltd.
The Report of Environmental Assessment and Reasons for Decision for the Selwyn Exploration Project at Howard's Pass, NT. This document was sent to the Minister of Indian and Northern Affairs July 3, 2009.
| Received: | Jul 6, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 78 |
| Stage: | Report of Environmental Assessment/Impact Review |
0.1 MBLetter of Clarification from GNWT
A letter from the GNWT clarifying recommendations made at the Tulita Communtiy Hearing.
| Received: | May 8, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 75 |
| Stage: | Other public registry materials |
0.1 MBLetter from Review Board to GNWT re: Request for Extension
Response from the Review Board to the GNWT regarding the request for extension of deadline for clarification of recommendation made at the Tulita hearing April 7th, 2009. Extension is granted to MAy 8th, 2009.
| Received: | Apr 30, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 74 |
| Stage: | Public hearings |
0.1 MBGNWT Request for Extension Letter
A request for extension letter from GNWT regarding the deadline for submission of clarification regarding a recommendation made in its presentation at the Tulita Communtiy Hearing on April 7th, 2009.
| Received: | Apr 29, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 73 |
| Stage: | Public hearings |
0.1 MBLetter to GNWT- Clarification Request
A letter from the Review Board to the GNWT requesting clarification on a point made at the Tulita Hearing April 7th, 2009. Upon receipt of this information by May 4th, 2009 the Review Board will begin deliberations on the information recieved throughtout the EA process.
| Received: | Apr 27, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 72 |
| Stage: | Other public registry materials |
0.06 MBNote to File -Closure of the Public Record
A note to file regarding the closure of the Selwyn Project Public Record.
| Received: | Apr 27, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 71 |
| Stage: | Other public registry materials |
1 MBFlying in Caribou Country-Referenced Document
This document by Yukon Environment has been referenced by Selwyn Resources as a guidance document for best practices. The developer is committed to using this document throughout the the entire operation in the Howard's Pass Area.
| Received: | Apr 21, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 70 |
| Stage: | Other public registry materials |
1 MBFlying in Sheep Country
A reference document put on the public record for the Selwyn environmental assessment. This paper was referred to by the developer during the assessment process.
| Received: | Apr 21, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 76 |
| Stage: | Public hearings |
0.1 MBResponse to Undertaking #1-Developer
During the Community Hearing in Tulita April 7th, 2009 two undertakings were issued by the the Review Board. This is the Developers response regarding the air emissions permit that the project has with the Yukon Territory.
| Received: | Apr 16, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 69 |
| Stage: | Public hearings |
0.07 MBNote to File -Audio Recording for Tulita Hearing
A Note to File regarding the availability of the audio recording from the Tulita Community Hearing held in Tulita April 7th, 2009.
| Received: | Apr 15, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 67 |
| Stage: | Public hearings |
0.4 MBResponse for Undertaking #2- Tulita Hearing
During the Community Hearing in Tulita April 7th, 2009 two undertakings were issued by the the Review Board. This is Indian and Northern Affairs response to Undertaking #2 regarding landwithdrawals for the Naats'ihch'oh National Park Reserve.
| Received: | Apr 15, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 68 |
| Stage: | Public hearings |
0.2 MBTulita Transcripts April 7th, 2009
Transcripts from the Selwyn Project- Howards Pass Environmental Assessment Community Hearing held April 7th, 2009 at the Arthur Mendo Arena, Tulita.
| Received: | Apr 9, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 66 |
| Stage: | Public hearings |
0.04 MBAgenda for Tulita Community Hearing April 7th, 2009
The Review Board is holding a community hearing for the Selwyn Environmental Assessment 0708-001. Attached is the agenda for the community hearing outlining the the schedule for the days proceedings.
| Received: | Apr 6, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 65 |
| Stage: | Public hearings |
0.07 MBAcceptance of Late Submissions Letter from Review Board
This is a notice to all parties of the Selwyn Project environmental assessment to accept or reject late submissions for the community hearing in Tulita, NT. All parties are advised to contact the Review Board by noon Friday April 3, 2009 if submissions are to be rejected.
| Received: | Apr 2, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 64 |
| Stage: | Public hearings |
5 MBCaribou Assessments Presentation-Tulita - Rick Farnell
A presentation submitted by Selwyn for the Tulita Community Hearing regarding the Caribou Assessment Research in the proposed area of exploration.
| Received: | Apr 2, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 63 |
| Stage: | Public hearings |
0.03 MBDFO statement for Tulita Hearing
Department of Fisheries and Ocean submitted a statement regarding the Selwyn Environmental Assessment for the Community Hearing being held in Tulita on April 7th, 2009.
| Received: | Apr 2, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 62 |
| Stage: | Public hearings |
5 MBSSI presentation for Tulita Hearing
Sahtu Secretariat Incorporated Lands and Resources submitted a presentation for the Tulita Community Hearing to be held in Tulita April 7th, 2009.
| Received: | Apr 2, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 61 |
| Stage: | Public hearings |
0.3 MBSelwyn -Developer's Presentation- Tulita Hearing
A brief presentation by the developer outlining the main issues to address in the Tulita Community Hearing.
| Received: | Apr 1, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 60 |
| Stage: | Public hearings |
0.4 MBGNWT Presentation - Selwyn EA Hearing - Tulita
GNWT presentation for the Selwyn EA Public Hearing in Tulita on April 7th sent into the Review Board March 31, 2009.
| Received: | Mar 31, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 54 |
| Stage: | Public hearings |
0.1 MBINAC Presentation for Selwyn Hearing in Tulita
A presentation from INAC for the Selwyn-Tulita Community Hearing April 7th, 2009.
| Received: | Mar 31, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 58 |
| Stage: | Public hearings |
0.4 MBParks Canada Presentation for Tulita Hearing
A presentation sent in from Parks Canada to be presented at the Selwyn-Tulita Community Hearing April 7th, 2009.
| Received: | Mar 31, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 59 |
| Stage: | Public hearings |
0.05 MBPresentation submission letter from Parks Canada
Submission cover letter preceding the presentation for the Tulita Hearing.
| Received: | Mar 31, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 57 |
| Stage: | Public hearings |
0.05 MBPWNHC Evidence - Selwyn EA Hearing - Tulita
GNWT included additional evidence to accompany their Tulita presentation. Included was a document from the Prince of Wales Northern Heritage Centre regarding the Selwyn Exploration area.
| Received: | Mar 31, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 55 |
| Stage: | Public hearings |
0.3 MBYESAB Recommendations March 2009
GNWT sent in a copy of the YESAB recommendations regarding the Selwyn licence renewal application for the Yukon portion of the project with their Tulita presentation.
| Received: | Mar 31, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 56 |
| Stage: | Public hearings |
0.05 MBNote to File re: March 23rd Pre-hearing Conference
A note to file regarding the pre-hearing conference that was held at the Review Board office on March 23, 2009. Document contains a list of attendees and information for the upcoming Hearing in Tulita.
| Received: | Mar 24, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 53 |
| Stage: | Public hearings |
0.2 MBNaats ihch'oh National Park Reserve Interim Withdrawal Map
A map indicating locations of the Naats'ihch'oh National Park Reserve Interim Withdrawal Area, Nahanni National park Reserve and its Expansion Interim Withdrawal, in the NWT and Yukon Region. This Map was submitted to the Review Board by Parks Canada.
| Received: | Mar 23, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 52 |
| Stage: | Other public registry materials |
0.2 MBAdditional Information for Parties on the PHC-Selwyn Project
Some additional information to prepare parties for the pre-hearing conference taking place March 23, 2009 at the Board Room of the Mackenzie Valley Review Board.
| Received: | Mar 6, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 51 |
| Stage: | Public hearings |
0.1 MBPre-Hearing Conference Date Change
Letter to the Selwyn Project distribution list announcing a date change for the Pre-hearing teleconference. This meeting is now to be held on Monday March 23, 2009 instead of March 20th as previously posted.
| Received: | Mar 5, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 50 |
| Stage: | Public hearings |
0.2 MBNotification of Pre-Hearing Conference
An announcement of the pre-hearing tele-conference for Selwyn Project Mineral Exploration EA. This tele-conference is to be held from the Board Room of the Mackenzie Valley Review Board on March 20th, 2009.
| Received: | Mar 4, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 49 |
| Stage: | Public hearings |
0.06 MBInvitation from MVEIRB to YESAB re: Tulita Community Hearing
Formal invitation extended to the Yukon Environmental and Socio-economic Assessment Board (YESAB) from The Review Board for the Selwyn Project Envirnomental Assessment Community Hearing in Tulita, NT. This hearing will be held on April 7, 2009.
| Received: | Feb 11, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 48 |
| Stage: | Other public registry materials |
0.1 MBCommunity Hearing Announcement for Selwyn EA
The following is a letter announcing the Selwyn Mineral Exploration Project community hearing in Tulita on April 7, 2009. Final issues will be heard by the Board from community and proponent.
| Received: | Feb 3, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 47 |
| Stage: | Public hearings |
0.4 MBLetter to MVEIRB from GNWT re: SARA
This letter, sent in on January 30, 2009, follows up on the correspondence between Environment Canada and the Review Board regarding duties under s.70(1) of the Species at Risk Act (SARA).GNWT provides a COSEWIC and SARA Summary Table.
| Received: | Jan 30, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 46 |
| Stage: | Other public registry materials |
0.02 MBLetter from EC to MVEIRB re: SARA Notification
Environment Canada provides additional information on threatened species and clarifies roles and responsibilities in this letter. It is a response to the notification letter sent by the Review Board to Environment Canada.
| Received: | Jan 23, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 45 |
| Stage: | Other public registry materials |
0.09 MBReview Board Letter to Environment Canada regarding SARA Notification for Selwyn Project
The Review Board has obligations under s. 79 of the Species at Risk Act to notify, during environmental assessments, the appropriate Minister if a project may potentially have an impact on a species at risk. This letter fulfills that responsibility for
| Received: | Jan 12, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 43 |
| Stage: | Other public registry materials |
0.3 MBSahtu Secretariat Inc. Letter to Review Board regarding Selwyn Project DAR
This letter is written on behalf of the Tulita District Land Corporation by the Sahtu Secretariat. It provides comments and suggestions on the DAR provided by Selwyn Resources for its proposed mineral exploration program at Howard's Pass.
| Received: | Jan 5, 2009 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 44 |
| Stage: | Information requests |
0.04 MBYESAB Letter to MVEIRB regarding Notification of Assessment
Letter from Yukon Environmental and Socio-economic Assessment Board (YESAB) notifying MVEIRB that Selwyn Resources Ltd. has applied to YESAB for assessment of the Selwyn Project (Advanced Exploration). Due to its location, the project may impact areas bo
| Received: | Dec 17, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 42 |
| Stage: | Other public registry materials |
0.07 MBResponse to Second Round Information Requests
This is Selwyn Resources' response to a second round of information requests issued by the Review Board on October 31st, 2008.
| Received: | Dec 5, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 41 |
| Stage: | Information requests |
0.02 MBRichard Hardy Letter to MVEIRB November 20
This letter confirms that Richard Hardy is no longer acting as legal counsel for the Tulita District Land Corporation, the Tulita Land Corporation, the Fort Norman Metis Land Corporation or the Norman Wells Land Corporation in the matter of the EA of Selw
| Received: | Nov 20, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 40 |
| Stage: | Other public registry materials |
0.008 MBNotice of Change of Address
Updated contact information for Selwyn Resources, the developer in this EA.
| Received: | Nov 17, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 39 |
| Stage: | Other public registry materials |
0.06 MBLetter to Mr. Richard Hardy from MVEIRB re: Extenstion granted
The Review Board has granted an extension to the Tulita District Land Corporation, the Tulita Land Corporation, the Fort Norman Metis Land Corporation and the Ernie MacDonald Land Corporation for the submission of IRs. This letter was previously pos
| Received: | Nov 5, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 38 |
| Stage: | Other public registry materials |
0.06 MBLetter to Tulita District Land Corporation from MVEIRB re: Extension Granted
The Review Board has granted an extension to the Tulita District Land Corporation, the Tulita Land Corporation, the Fort Norman Metis Land Corporation and the Ernie MacDonald Land Corporation for the submission of IRs. This letter was previously posted, b
| Received: | Nov 5, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 37 |
| Stage: | Other public registry materials |
0.1 MBSecond Round Information Requests for Selwyn Resources Ltd.
This document contains the second round of information requests from the Mackenzie Valley Review Board pertaining to the environmental assessment of Selwyn Resources Ltd.'s Mineral Exploration at Howard's Pass (Selwyn Project). The due date for the respon
| Received: | Oct 31, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 35 |
| Stage: | Information requests |
0.02 MBSelwyn Stream in NWT - picture 15964
One of several pictures submitted by DFO that show representative streams of the type that will be used by the developer for water withdrawals.
| Received: | Oct 30, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 27 |
| Stage: | Information requests |
0.03 MBSelwyn Stream in NWT - picture 15965
One of several pictures submitted by DFO that show representative streams of the type that will be used by the developer for water withdrawals.
| Received: | Oct 30, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 28 |
| Stage: | Information requests |
0.03 MBSelwyn Stream in NWT - picture 15966
One of several pictures submitted by DFO that show representative streams of the type that will be used by the developer for water withdrawals.
| Received: | Oct 30, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 29 |
| Stage: | Information requests |
0.03 MBSelwyn Stream in NWT - picture 15967
One of several pictures submitted by DFO that show representative streams of the type that will be used by the developer for water withdrawals.
| Received: | Oct 30, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 30 |
| Stage: | Information requests |
0.03 MBSelwyn Stream in NWT - picture 15968
One of several pictures submitted by DFO that show representative streams of the type that will be used by the developer for water withdrawals.
| Received: | Oct 30, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 31 |
| Stage: | Information requests |
0.03 MBSelwyn Stream in NWT - picture 15969
One of several pictures submitted by DFO that show representative streams of the type that will be used by the developer for water withdrawals.
| Received: | Oct 30, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 32 |
| Stage: | Information requests |
0.03 MBSelwyn Stream in NWT - picture 15970
One of several pictures submitted by DFO that show representative streams of the type that will be used by the developer for water withdrawals.
| Received: | Oct 30, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 33 |
| Stage: | Information requests |
0.05 MBLetter from MVEIRB re: Party status applications
This letter informs organizations that they have been granted party status to EA0708-001, Selwyn Resources' proposed mineral exploration at Howard's Pass.
| Received: | Oct 29, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 36 |
| Stage: | Other public registry materials |
0.03 MBSelwyn Resources First IR Response
This is a response to the Information Request issued by the Review Board to Selwyn Resources.
| Received: | Sep 23, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 25 |
| Stage: | Information requests |
0.02 MBEmail between DFO and Selwyn Resources Regarding Water Quality Impacts
Additional information provided by the Department of Fisheries and Oceans.
| Received: | Sep 8, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 26 |
| Stage: | Information requests |
0.4 MBParty Status Request Form
Call for Party Status and IR, MVEIRB IR Template, Party Status Request Form
| Received: | Aug 26, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 24 |
| Stage: | Information requests |
5 MBFinal Developer's Assessment Report - Selwyn Resources Ltd. - Mineral Exploration at Howard's Pass
Final Developer's Assessment Report for Selwyn Resources Ltd. - Mineral Exploration at Howard's Pass.
| Received: | Aug 25, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 34 |
| Stage: | Developer's Assessment Report/Environmental Impact Statement |
0.06 MBInformation Request for Selwyn Resources Ltd.
Issued by the Review Board on August 25, 2008.
| Received: | Aug 25, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 22 |
| Stage: | Information requests |
0.02 MBLetter from MVEIRB to Selwyn Resources re: Conformity of DAR
On June 27, 2008, the Review Board received a Developers Assessment Report from Selwyn Resources. This letter is to confirm that the DAR is in conformity with the Terms of Reference issued in January.
| Received: | Aug 5, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 18 |
| Stage: | Developer's Assessment Report/Environmental Impact Statement |
1 MBAppendix I SOPs
Appendices to the developers assessment report.
| Received: | Jun 27, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 12 |
| Stage: | Developer's Assessment Report/Environmental Impact Statement |
2 MBAppendix II MSDS
Appendices to the developers assessment report.
| Received: | Jun 27, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 13 |
| Stage: | Developer's Assessment Report/Environmental Impact Statement |
0.9 MBAppendix III YT Waste Management Plans & Permits
Appendices to the developers assessment report.
| Received: | Jun 27, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 14 |
| Stage: | Developer's Assessment Report/Environmental Impact Statement |
0.3 MBAppendix IV Native Seed Mix
Appendices to the developers assessment report.
| Received: | Jun 27, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 15 |
| Stage: | Developer's Assessment Report/Environmental Impact Statement |
3 MBAppendix V Consultation
Appendices to the developers assessment report.
| Received: | Jun 27, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 16 |
| Stage: | Developer's Assessment Report/Environmental Impact Statement |
10 MBAppendix VI TK Study
Appendices to the developers assessment report.
| Received: | Jun 27, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 17 |
| Stage: | Developer's Assessment Report/Environmental Impact Statement |
0.03 MBAppendix VII Issue Tracking and responses Draft July 15
Appendices to the developers assessment report.
| Received: | Jun 27, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 19 |
| Stage: | Developer's Assessment Report/Environmental Impact Statement |
4 MBDeveloper's Assessment Report (June 16 2008)
This Developer's Assessment Report was received at the Review Board office on June 27, 2008. Staff is completing a conformity check and will be asking for party comments after this is completed.
| Received: | Jun 27, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 11 |
| Stage: | Developer's Assessment Report/Environmental Impact Statement |
0.07 MBFinal Terms of Reference
This document is the final Terms of Reference for the environmental assessment of Selwyn Resources' proposed mineral exploration program at Howard's Pass. It gives direction to the developer on what information to include in their Developers Assessment R
| Received: | Jan 25, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | N/A |
| Stage: | Terms of Reference and workplans |
0.06 MBComments from Parks Canada
Comments provided by Parks Canada on the draft Terms of Reference for the environmental assessment of Selwyn Resources' proposed mineral exploration program at Howard's Pass.
| Received: | Jan 17, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 9 |
| Stage: | Terms of Reference and workplans |
0.2 MBComments from Indian and Northern Affairs
Comments provided by INAC on the draft Terms of Reference for the environmental assessment of Selwyn Resources' proposed mineral exploration program at Howard's Pass.
| Received: | Jan 15, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | N/A |
| Stage: | Terms of Reference and workplans |
0.1 MBComments from Selwyn Resources
Comments provided by the developer on the draft Terms of Reference for the environmental assessment of its proposed mineral exploration program at Howard's Pass.
| Received: | Jan 14, 2008 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 10 |
| Stage: | Terms of Reference and workplans |
0.07 MBDraft Terms of Reference
This document gives direction to the developer on what information to include in their developer's assessment report for Selwyn Resources mineral exploration program at Howard's Pass. Comments on this draft document are due January 15, 2008 and may be for
| Received: | Dec 21, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | N/A |
| Stage: | Terms of Reference and workplans |
0.08 MBFinal Workplan
This is the final workplan for the EA of Selwyn Resources' proposed mineral exploration at Howard's Pass.
| Received: | Nov 21, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 4 |
| Stage: | Scoping |
0.02 MBComments from Developer re: Draft Workplan
Comments from Selwyn Resouces related to the draft workplan issued by the Review Board for the EA of Selwyn Resources proposed mineral exploration program at Howard's Pass.
| Received: | Nov 8, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 7 |
| Stage: | Scoping |
0.07 MBComments from INAC re: Draft Workplan
Comments from INAC related to the draft workplan issued by the Review Board for the EA of Selwyn Resources proposed mineral exploration program at Howard's Pass.
| Received: | Nov 7, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 8 |
| Stage: | Scoping |
0.009 MBComments re: Draft Workplan
These comments were received by MVEIRB from the legal counsel for the Tulita District Land Corp., Rick Hardy. They are in response to the Draft Workplan issued by the Review Board for the EA of Selwyn Resources' proposed mineral exploration at Howard's Pa
| Received: | Nov 4, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | N/A |
| Stage: | Scoping |
0.07 MBDraft Workplan
This is the draft workplan for the EA of Selwyn Resources planned mineral explroation program. The comment period for this draft workplan ends on November 7th, 2007.
| Received: | Oct 31, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 4 |
| Stage: | Scoping |
0.2 MBScoping Session in Tulita
The document is a list of some issues raised in Tulita, during scoping sessions held on Oct 10th, 2007.
| Received: | Oct 10, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 5 |
| Stage: | Scoping |
0.2 MBLetter from MVEIRB to Distribution List re: Scoping Sessions
This letter invites individuals and organizations to attend a scoping session in Tulita on October 10th, 2007.
| Received: | Sep 6, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 3 |
| Stage: | Scoping |
0.1 MBFax to Dehcho First Nations from MVEIRB re: Notification of EA
Fax to the Dehcho First Nations notifying this organization of the EA of Selwyn Resources' mineral exploration at Howard's Pass.
| Received: | Aug 3, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | 6 |
| Stage: | Assessment/review startup |
0.01 MBEmail from Selwyn Resources
The developer indicates that they will be unable to participate in the EA for their proposed development at Howard's Pass until early September due to other commitments.
| Received: | Jul 31, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 2 |
| Stage: | Scoping |
0.1 MBLetter to Tulita Land Corp from MVEIRB re: Community Scoping Session
Letter requests community availability for a possible scoping exercise in Tulita. This would be the first step in the evironmental assessment of Selwyn Resources' Howard's Pass development.
| Received: | Jul 5, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | N/A |
| Stage: | Scoping |
0.03 MBUpdate email from Selwyn Resources
Correspondance between MVEIRB and Selwyn Resources regarding the environmental assessment of Selwyn Resources Howard's Pass development.
| Received: | Jul 4, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Parties/Public |
| Public Registry: | 1 |
| Stage: | Assessment/review startup |
0.03 MBInitial Distribution List
Contact information for stakeholders who were notified of the startup of EA0708-001, Selwyn Resources' Mineral Exploration at Howard's Pass.
| Received: | Jun 19, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | N/A |
| Stage: | Assessment/review startup |
0.5 MBMap of Project Area
Map showing the claims and lease blocks where Selwyn Resources proposes to conduct their Howard's Pass exploration program.
| Received: | Jun 18, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Other |
| Public Registry: | 23 |
| Stage: | Assessment/review startup |
0.09 MBNotice of Referral to Developer
This letter gives notice to Selwyn Resources that their mineral exploration project at Howard's Pass has been referred to EA.
| Received: | Jun 18, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | N/A |
| Stage: | Assessment/review startup |
0.1 MBNotice of Referral to Distribution List
General notice of referral to Environmental Assessment.
| Received: | Jun 18, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Review Board |
| Public Registry: | N/A |
| Stage: | Assessment/review startup |
0.1 MBLetter from Sahtu Secretariat Inc. to MVEIRB re: Referral to EA
This letter refers Selwyn Resources' Howard's Pass area mineral exploration project to EA pursuant to MVRMA s.126(2)(b).
| Received: | Jun 8, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Other |
| Public Registry: | 21 |
| Stage: | Assessment/review startup |
10 MBLand Use Permit Application
Selwyn Resources LUP application to the Sahtu Land and Water Board
| Received: | Apr 2, 2007 |
|---|---|
| Document Date: | Unknown |
| Originator: | Developer |
| Public Registry: | 20 |
| Stage: | Preliminary screening |
Total Number of Documents: 89