GNWT-INF Tłı̨chǫ All Season Road - EA-1617-01
Environmental Assessment - Complete
22 results from this project
Technical reports
Sep 29, 2017
Draft geotechnical investigation of granular and bedrock prospects for the Tlicho All Season Road. Document split into eight parts due to size (PR#200-PR#208). Part 4 of 9 - appendix e part 2.
Technical reports
Sep 29, 2017
Draft geotechnical investigation of granular and bedrock prospects for the Tlicho All Season Road. Document split into eight parts due to size (PR#200-PR#208). Part 5 of 9 - appendix e part 3.
Technical reports
Sep 29, 2017
Draft geotechnical investigation of granular and bedrock prospects for the Tlicho All Season Road. Document split into eight parts due to size (PR#200-PR#208). Part 6 of 9 - appendix e part 4.
Technical reports
Sep 29, 2017
Draft geotechnical investigation of granular and bedrock prospects for the Tlicho All Season Road. Document split into eight parts due to size (PR#200-PR#208). Part 8 of 9 - appendix e part 6.
Technical reports
Sep 29, 2017
Draft geotechnical investigation of granular and bedrock prospects for the Tlicho All Season Road. Document split into eight parts due to size (PR#200-PR#208). Part 7 of 9 - appendix e part 5.
Technical reports
Sep 29, 2017
Draft geotechnical investigation of granular and bedrock prospects for the Tlicho All Season Road. Document split into eight parts due to size (PR#200-PR#208). Part 9 of 9 - appendices f-h.
Technical or community sessions
Sep 28, 2017
Additional boreal caribou maps and narrative for figures in the GNWT response to ECCC IR#7. Provided in response to commitment 9 from the technical session.
Technical reports
Sep 27, 2017
Bathurst caribou range plan interim discussion documents, submitted to the Review Board registry by the GNWT at the request of WRRB.
Technical reports
Sep 27, 2017
Species status report on the porcupine caribou and barren-ground caribou in the NWT, submitted to the Review Board registry by GNWT at the request of WRRB.
Technical or community sessions
Sep 26, 2017
The Government of Northwest Territories provided a note along with the submission of the Cluff et al. 2017 unpublished draft report (PR#195 and #196) that GNWT referenced in its response to commitment 3 (PR#189, #190).
Technical or community sessions
Sep 26, 2017
Unpublished draft of 'Calf production and adult sex ratio in the bathurst and bluenose east herds of barren-ground caribou' report by Cluff et al. 2017. Referenced by GNWT in its response to commitment 3 (PR#189, #190). An accompanying note from GNWT can be found in PR#194 and the appendices are in PR#196.
Technical or community sessions
Sep 26, 2017
Appendices to go with PR#195.
Technical or community sessions
Sep 25, 2017
Summary of relevant findings from archaeological work completed at 13 potential borrow pits. Provided in response to commitment 22 from the August technical sessons in Behchoko.
Technical reports
Sep 22, 2017
Government of Northwest Territories cover letter for the September 22 submission of the updated draft Wildlife Management and Monitoring Plan.
Technical reports
Sep 22, 2017
Government of Northwest territories updated draft Wildlife Management and Monitoring Plan, September 2017.
Technical Reports
Sep 18, 2017
Meeting report between the GNWT and WRRB to discuss the WRRBs request for extension for their Technical report. Meeting occurred September 11, 2017.
Technical or community sessions
Sep 18, 2017
GNWTs response to technical session commitment 3 about caribout distribution. Associated maps can be found in PR#190.
Technical or community sessions
Sep 18, 2017
Caribou distribution data maps associated with PR#189 (response to technical session commitment 3).
Technical reports
Sep 15, 2017
A meeting report for a meeting between Government of Northwest Territories, Natural Resources Canada, and the Northern Projects Management Office related to the storage and use of explosive for EA1617-01.
Technical reports
Sep 15, 2017
Natural Resources Canada guidelines for bulk explosives facilities minimum requirements, February 2014.
Technical reports
Sep 15, 2017
Government of Canada explosives regulations, 2013.
Technical reports
Sep 14, 2017
Presentation for the technical report preparation meeting on September 14, 2017.
Canadian Zinc Corporation Prairie Creek All Season Road - EA1415-01
Environmental Assessment - Complete
3 results from this project
Post Report Materials
Sep 28, 2017
Note to file about the September 27, 2017, meeting to describe the measures in the Report of Environmental Assessment.
Post Report materials
Sep 19, 2017
Note to file about the September 18, 2017, meeting to describe the measures in the Report of Environmental Assessment.
Post Report materials
Sep 15, 2017
Dates and times for presentation of Report of EA measures