A new Public Registry is Now Live. We are also thrilled to announce the soft-launch of our new website, where you can access our new public registry. We would love your feedback. For a seamless experience and to stay updated with the latest information, simply click the button below to toggle between both sites. We look forward to seeing you around!

EA1819-01 Depositing Processed Kimberlite in Pits and Underground

« Back to ProjectGo to Timeline Tracker »

Start and End Date: 
Feb 19 2019 to Jan 6 2020
To DateTotal ProjectedParty
3 months3 months Developer
7.5 months7.5 months MaxBoard/Parties
5 months5 months Minister
15.5 months15.5 monthsTotal
Legend
Developer to date Board/Parties to date Minister to date
projected projected projected

Max bar indicates the maximum timeline threshold for Board/Parties (16 months).

Slide and stretch the yellow box in the miniature timeline to adjust the zoom and/or time period you can see.
The milestones at the grey dots include links to registry documents.