Taltson Hydroelectric Expansion Project - EA0708-007

Document List - Post Report materials

Displaying 16 documents.
42.64 KB

This is a letter from the Review Board approving the termination of the Deze envrionmental assessment at the request of NT Energy, managing partner for Deze Energy Corp.

58.92 KB

This letter from NWT Energy Corp, managing partner of Deze Energy Corp, requests that the Board conclude the Deze EA.process.

66.38 KB

This letter from the Review Board agrees to Deze's proposed six-month extension and describes information the Board will need by July 2013 to consider further adjournment.

78.11 KB

This is a response from Deze to the Review Board's Oct. 5 2012 letter.

30.77 KB

The following document is a letter from the Review Board to Deze Energy Corporation regarding a definitive prediction for further information on the Taltson Hydroelectric Expansion Project.

56.81 KB

Taltson Hydro Expansion Project Update letter-August 30, 2012

265.88 KB

This letter from the Review Board asks Deze Energy for an update on the project status of the Taltson expansion project.

296.26 KB

A letter to the Review Board from Deze Energy regarding the on-going investigation of transmission routing. This is an update from the company .

121.67 KB

This a note to file regarding the developers request for extension of the revised routing proposal.

723.73 KB

This letter from Deze requests that the deadline for its revised routing submission be extended from February 7th to March 7th, 2011.

901.53 KB

This letter from the Review Board to parties re-opens the record for the environmental assessment. It requests information from Deze by Feb. 7th, 2011.

272.27 KB

This is a letter from the Review Board responding to INAC's letter of Dec. 10 2010.

1.32 MB

This letter states that the Responsible Ministers have referred the Deze Report of Environmental Assessment back to the Review Board for further consideration.

25.17 KB

This is a letter from LKDFN to the INAC Minister regarding the Review Board's recommendation on the Deze project.

91 KB

These are two letters from INAC dated Aug. 10th and 17th, 2010, acknowledging receipt of the Report of EA for the Taltson project.

158.32 KB

This is a draft Terms of Reference released by Deze for its Advisory Routing Committee.